BI-ANNUAL COMPREHENSIVE PLAN AMENDMENT CYCLE

Amendment No. 04-1

Tentative Schedule

 

Date

Time

Location

Action

April 15, 2003

 

 

Application due date

November 4, 2003

6:30

NPR

Public Hearing for BCC sitting as the LPA

November 18, 2003

6:30

DC

Public Hearing for BCC Transmittal of Comp Plan Amendments

December 9, 2003

 

 

Transmit 3 copies of the plan amendment package to FDCA and 1 copy to each of the reviewing agencies pursuant to 9J-11.006, FAC.

December 16, 2003

 

 

FDCA provides notification of completeness (five working days)

January 16, 2004

 

 

30-day review by State agencies, TBRPC and interested parties completed

January 21, 2004

 

 

FDCA provides notification of decision to review (35 days after receipt of amendment package)

February 17, 2004

 

 

FDCA issues ORC (60 days after receipt of amendment proposal), adoption occurs within 60 days

March 23, 2004

1:30

DC

Introduction of Ordinances

April 14, 2004

6:30

NPR

BCC Adoption Public Hearing (Amendment and Ordinance)

April 28, 2004

 

 

Transmit 3 copies of adopted plan amendment package to FDCA and 1 copy to each of the reviewing agencies pursuant to 9J-11.011, FAC.

May 3, 2004

 

 

FDCA receives amendment package

June 17, 2004

 

 

FDCA issues NOI (45 days after receipt of adopted plan amendment, if found in compliance)

July 8, 2004

 

 

Expiration Date of 21-day appeal period

July 8, 2004

 

 

Effective date of Comp Plan Amendment (provided no appeal filed)