DEVELOPMENT REVIEW COMMITTEE, PASCO COUNTY, FLORIDA
A G E N D A
DECEMBER 23, 2004
1:30 p.m. ‑ West Pasco Government Center, Board Room,
7530 Little Road, New Port Richey, FL 34654-5598
_______________________________________________________________________________________
DEVELOPMENT REVIEW COMMITTEE
John J. Gallagher
County Administrator
Michael Nurrenbrock
OMB Director
Daniel R. Johnson
Assistant County Administrator
(Public Services)
Bruce E. Kennedy, P.E.
Acting Assistant County Administrator
(Utilities Services)
Bipin Parikh, P.E.
Assistant County Administrator
(Development Services)
Michael Rapp
District School Board of Pasco County
LEGAL COUNSEL
Robert D. Sumner
County Attorney
ADVISORY STAFF
Cynthia M. Jolly, P.E.
Development Director
Debra M. Zampetti
Zoning/Code Compliance
Administrator
Vacant
Development Review Manager
Samuel P. Steffey II
Growth Management Administrator
James C. Widman, P.E.
Engineering Services Director
Representative of the Clerk
of the Circuit Court
________________________________________________________________________________________
I. OPENING
II. ROLL CALL
III. MINUTES
None
IV. VARIANCE PETITIONS
A. Public Hearing
Proof of Publication
B. Variance Review
The Development Review Committee may grant a variance from the terms of the Land Development Code when such variance will not be contrary to the public interest; where, owing to special conditions, a literal enforcement of the provisions of this code would result in unnecessary hardship or where improved or alternative technology would meet or exceed the development and construction standards set forth in this code. Such variance shall not be granted if it has the effect of nullifying the intent and purpose of this code. Furthermore, such variance shall not be granted by the Development Review Committee unless and until a variance application is submitted demonstrating compliance with one or more of the following:
1. That special conditions and circumstances exist which are peculiar to the land, structures, or required subdivision improvements involved, and which are not applicable to other lands, structures, or required improvements.
2. That a literal interpretation of the provisions of this code would deprive the applicant of rights commonly enjoyed by other properties with similar conditions.
3. That the actions of the applicant did not cause the special conditions and circumstances which necessitate the variance.
4. That the granting of the variance requested will not confer on the applicant any special privilege that is denied by this code to other lands, structures, or required improvements under similar conditions.
5. Through improved or alternative technology, the development and construction standards set forth in this code are met or exceeded.
6. The Development Review Committee finds that the requirements of this code have been met based upon the review and findings of the Development Review Services Department and information presented at a public hearing.
7. The Development Review Committee further finds that the reasons set forth in the application justify the granting of the variance that would make possible the reasonable use of the land, buildings, or other improvements.
8. The Development Review Committee finds that the granting of the variance would be in harmony with the general standards, purpose, and intent of this code and will not be injurious to the surrounding territory, or otherwise be detrimental to the public welfare.
9. The Development Review Committee finds that the granting of the variance would not violate the Goals, Objectives, and Policies of the Comprehensive Plan.
a. Memorandum No.: DR05‑183
Project Name: Hudson Storage
Commissioner: The Honorable Jack Mariano
Applicant: Hudson Storage USA, LLC
Location: On the southwest corner of U.S. 19 and Sea Ranch Drive, Section 33, Township 24 South, Range 16 East.
Acreage: 6.08 Acres, m.o.l.
Proposed Development: Eight office/self-storage buildings, totaling 70,950 square feet.
Requested: A variance from Sections 603.7.A and B, Building Perimeter Landscaping, of the Pasco County Land Development Code.
RECOMMENDATION: Continue to the April 28, 2005, Development Review Committee meeting, at 1:30 p.m., in New Port Richey.
b. Memorandum No.: DR05‑423
Project Name: Tucker Woods
Commissioner: The Honorable Ted Schrader
Applicants: Lewis P. and Marlene Mann
Location: In East Pasco County, on the south side of Tucker Road, at the intersection of Peaceful Lane and Tucker Road, Section 22, Township 26 South, Range 21 East.
Acreage: 14.03 Acres, m.o.l.
Proposed
Development: The developers are requesting preliminary/
construction plan and Stormwater Management Plan and Report approval for the
division of 14.03 acres into 18 single-family lots.
Requested: Relief from Land Development Code Section 602.7.C.2.b, Tree Plans, Replacement.
RECOMMENDATION: Continue to the January 27, 2005, Development Review Committee meeting, at 1:30 p.m., in Dade City.
c. Memorandum No.: DR05‑446
Project Name: Suncoast Crossings, Parcel B, Phase II
Commissioner: The Honorable Ann Hildebrand
Applicant: MDG Suncoast, LLC
Location: On the southwest corner of the Suncoast Parkway and S.R. 54, Sections 30 and 31, Township 26 South, Range 18 East.
Acreage: 23.78 Acres, m.o.l.
Proposed Development: 180,390 square feet of retail.
Requested: A variance from Section 603.7, Building Perimeter Landscaping, of the Pasco County Land Development Code which, if approved, would allow a portion of the required landscaping for the proposed buildings to be planted elsewhere on the project site.
RECOMMENDATION: Approval with conditions.
d. Memorandum No.: DR05‑466
Project Name: General Cabinets Warehouse
Commissioner: The Honorable Jack Mariano
Applicant: Donald Josephik
Location: On the northwest corner of Casper Avenue and Archer Street (Hudson area), Section 24, Township 24 South, Range 24 East.
Acreage: 1.53 Acres, m.o.l.
Proposed Development: Office/warehouse (3,200 square feet).
Requested: Variance from Pasco County Land Development Code, Section 603.7, Building Perimeter Landscaping, to allow the owner to install 717 square feet of required building perimeter landscaping for the existing building around the proposed building. This would be in addition to the required 320 square feet around the proposed building.
RECOMMENDATION: Approval.
Pages 1-22
V. APPEALS
A. Class I
None Scheduled
B. Class II
None Scheduled
C. Class III
None Scheduled
D. Class IV
None Scheduled
E. Consistency
None Scheduled
VI. PUBLIC NOTICE AGENDA
A. Proof of Public Notice
B. Class II
1. Memorandum No.: DR05‑511
Project Name: Alumi-Guard, Phase III
Commissioner: The Honorable Jack Mariano
Location: On the north side of New York Avenue, approximately 140 feet east of Ohma Street, Section 23, Township 24 South, Range 16 East.
Acreage: 19.82 Acres, m.o.l.
Proposed Development: To construct a 167,250-square-foot office/warehouse building.
RECOMMENDATION: Continue to the January 27, 2005, Development Review Committee meeting, at 1:30 p.m., in Dade City.
2. Memorandum No.: DR05‑512
Project Name: Broedell Plumbing
Continued from the November 4, 2004, and December 9, 2004, Development Review Committee Meetings)
Commissioner: The Honorable Ann Hildebrand
Location: On the north side of S.R. 54, approximately 400 feet east of the Mitchell Ranch Road intersection (Elfers area), Section 23, Township 26 South, Range 16 East.
Acreage: 3.82 Acres, m.o.l.
Proposed Development: To construct a 54,091-square-foot plumbing supply store.
RECOMMENDATION: Continue to the February 24, 2005, Development Review Committee meeting, at 1:30 p.m., in New Port Richey.
3. Memorandum No.: DR05‑513
Project Name: Cypress Creek, Phase 4, Infrastructure
Commissioner: The Honorable Pat Mulieri, Ed.D.
Location: On the northeast corner of the intersection of I‑75 and S.R. 56, Section 26, Township 26 South, Range 19 East.
Acreage: 34.1 Acres, m.o.l.
Proposed Development: To construct infrastructure for 14 lots, including stormwater ponds.
RECOMMENDATION: Continue to the January 13, 2005, Development Review Committee meeting, at 1:30 p.m., in New Port Richey.
4. Memorandum No.: DR05‑514
Project Name: Ed Morse Auto Plaza Addition
(Continued from the November 18, 2004, Development Review Committee Meeting)
Commissioner: The Honorable Jack Mariano
Location: On the northwest corner of the intersection of U.S. 19 and Graphic Drive, Section 16, Township 25 South, Range 16 East.
Acreage: 11.48 Acres, m.o.l.
Proposed Development: To construct a 4,225-square-foot showroom building, totaling 52,160 square feet, and a 9,381 additional square feet of canopy space.
RECOMMENDATION: Approval with conditions.
5. Memorandum No.: DR05‑515
Project Name: Hudson Storage
Commissioner: The Honorable Jack Mariano
Location: On the southeast corner of Sea Ranch Drive and Delmor Drive (Hudson area), Section 33, Township 24 South, Range 16 East.
Acreage: 6.08 Acres, m.o.l.
Proposed Development: To construct eight office/storage buildings, totaling 70,950 square feet.
RECOMMENDATION: Continue to the April 28, 2005, Development Review Committee meeting, at 1:30 p.m., in New Port Richey.
6. Memorandum No.: DR05‑516
Project Name: Pall Aeropower Parking Lot Expansion
Commissioner: The Honorable Steve Simon
Location: On the south side of Ridge Road, opposite Kitty Hawk Drive (New Port Richey area), Section 30, Township 25 South, Range 17 East.
Acreage: 53.86 Acres, m.o.l. (Project Area Approximately 2 Acres)
Proposed Development: To construct a parking lot expansion.
RECOMMENDATION: Approval with conditions.
7. Memorandum No.: DR05‑517
Project Name: Pasco County Sheriff's Forensics Building
Commissioner: The Honorable Pat Mulieri, Ed.D.
Location: On the east end of Central Boulevard (Land O' Lakes area), Section 14, Township 25 South, Range 18 East.
Acreage: 68.49 Acres, m.o.l.
Proposed Development: To construct a 21,544-square-foot Sheriff's forensics building.
RECOMMENDATION: Continue to the January 27, 2005, Development Review Committee meeting, at 1:30 p.m., in Dade City.
8. Memorandum No.: DR05‑518
Project Name: Seven Oaks, Parcel S‑20
(Continued from the November 4, 2004, and November 18, 2004, Development Review Committee Meetings)
Commissioner: The Honorable Pat Mulieri, Ed.D.
Location: On the west side of Ancient Oaks Boulevard, approximately 1,300 feet north of S.R. 56, Section 25, Township 26 South, Range 19 East.
Acreage: 90.82 Acres, m.o.l. (7.73 Acres Project Area)
Proposed Development: To construct 29 professional/office buildings, totaling 77,280 square feet.
RECOMMENDATION: Approval with conditions.
9. Memorandum No.: DR05‑519
Project Name: Suncoast Crossings, Phase B2/Target
(Continued from the October 28, 2004, and December 9, 2004, Development Review Committee Meetings)
Commissioner: The Honorable Ann Hildebrand
Location: On the southeast corner of the intersection of S.R. 54 and Crossings Boulevard, Sections 30 and 31, Township 26 South, Range 18 East.
Acreage: 31.01 Acres, m.o.l.
Proposed Development: To construct 190,988 square feet of retail space, including a Target, garden center, and 6,500‑square-foot out-parcel.
RECOMMENDATION: Approval with conditions.
10. Memorandum No.: DR05‑520
Project Name: Sweetwater Apartments
Commissioner: The Honorable Ted Schrader
Location: On the north end of Janke Road (Dade City area), Section 05, Township 25 South, Range 21 East.
Acreage: 43.44 Acres, m.o.l.
Proposed Development: To construct a 176-unit apartment complex with amenities (16 buildings total).
RECOMMENDATION: Continue to the January 13, 2005, Development Review Committee meeting, at 1:30 p.m., in New Port Richey.
11. Memorandum No.: DR05‑521
Project Name: Tropical Village Addition
(Continued from the November 4, 2004, Development Review Committee Meeting)
Commissioner: The Honorable Pat Mulieri, Ed.D.
Location: On the southeast corner of the intersection of U.S. 41 and Lake Floyd Drive (Lutz area), Section 36, Township 26 South, Range 18 East.
Acreage: 3.76 Acres, m.o.l.
Proposed Development: To construct two 3,000-square-foot office buildings, totaling 22,800 square feet.
RECOMMENDATION: Continue to the January 13, 2005, Development Review Committee meeting, at 1:30 p.m., in New Port Richey.
12. Memorandum No.: DR05‑0493
Project Name: Southern Peat Mine
Commissioner: The Honorable Ted Schrader
Location: 1‑75 and Darby Road, Sections 05, 06, 08, 31, and 32, Townships 24 and 25 South, Range 20 East.
Acreage: 1,667.5 Acres, m.o.l.
Proposed Development: The applicant is proposing to harvest approximately 1,385,000 cubic yards of peat within 772 acres of the total 1,667.5 acres for a period of 25 years.
RECOMMENDATION: Approval with conditions.
13. Memorandum No.: DR05‑522
Project Name: Wesley Chapel Toyota
Commissioner: The Honorable Pat Mulieri, Ed.D.
Location: On the southeast corner of the intersection of I‑75 and S.R. 54, Sections 07 and 12, Township 26 South, Ranges 19 and 20 East.
Acreage: 74.19 Acres, m.o.l.
Proposed Development: To construct a two-building, 93,057-square-foot, automobile dealership and collision center.
RECOMMENDATION: Continue to the January 27, 2005, Development Review Committee meeting, at 1:30 p.m., in Dade City.
C. Class III
1. Memorandum No.: DR05‑503
Project Name: Asbel Creek, Phase V
Commissioner: The Honorable Pat Mulieri, Ed.D.
Location: Approximately one-quarter mile west of U.S. 41, on the north side of Asbel Road (Land O' Lakes are), Sections 16 and 21, Township 25 South, Range 18 East.
Acreage: 51.16 Acres, m.o.l.
Proposed Development: The developer requests preliminary/construction plan and Stormwater Management Plan and Report approval to subdivide 51.16 acres into 93 single-family detached lots.
RECOMMENDATION: Because additional plan revisions are required, the DRD recommends continuing this to the January 13, 2005, Development Review Committee meeting, at 1:30 p.m., in New Port Richey.
2. Memorandum No.: DR05‑488
Project Name: Tucker Woods
(Continued from the November 4, 2004, Development Review Committee Meeting)
Commissioner: The Honorable Ted Schrader
Location: In East Pasco County, on the south side of Tucker Road, at the intersection of Tucker Road and Peaceful Lane, Section 22, Township 26 South, Range 21 East.
Acreage: 14.03 Acres, m.o.l.
Proposed Development: The developer is requesting preliminary/construction plan and Stormwater Management Plan and Report approval for the division of 14.03 acres into 18 single-family lots.
RECOMMENDATION: Continue to the January 27, 2005, Development Review Committee meeting, at 1:30 p.m., in Dade City.
Pages 23-80
VII. REGULAR AGENDA
A. Class II
None Scheduled
B. Class III
1. Memorandum No.: DR05‑0492
Project Name: Ledantec, Phase 1, Units A and B
Commissioner: The Honorable Pat Mulieri, Ed.D.
Location: On the north side of S.R. 54, approximately three miles east of the Suncoast Parkway, Sections 21 and 22, Township 26 South, Range 18 East.
Acreage: 96.5 Acres, m.o.l.
Proposed Development: The applicant is requesting construction/stormwater plan approval to construct 139 single-family lots.
RECOMMENDATION: Approval with conditions.
C. Class IV
None Scheduled
D. Utilities
None Scheduled
VIII. CONSISTENCY DETERMINATIONS
None Scheduled
IX. DISCUSSION
A. Discussion of Policy Issues
None Scheduled
X. INFORMATION
None Scheduled
XI. NOTED ITEMS
A. CLASS I Development Actions from December 10, 2004, to December 15, 2004:
1. Memorandum No.: DR05‑296
Project Name: WPIP, Phase 3, Lot 24
Commissioner: The Honorable Ann Hildebrand
Applicant: Southern Diamond Holdings, Inc.
Location: On the south side of Cargo Court, approximately 200 feet east of Merchant Avenue, Section 29, Township 26 South, Range 17 East.
Acreage: 0.93 Acre, m.o.l.
Proposed Development: 8,000 square feet of retail.
Type of Action: Approval.
Date of Action: December 10, 2004
2. Memorandum No.: DR05‑218
Project Name: Children's Speech Services, Inc.
Commissioner: The Honorable Steve Simon
Applicant: Children's Speech Services, Inc.
Location: Approximately 200 feet south of Ridge Road and Tanglewood Drive, on the east side of Tanglewood Drive (West Pasco), Section 25, Township 25 South, Range 16 East.
Acreage: 1.03 Acres, m.o.l.
Proposed Development: Special therapy professional office.
Type of Action: Approval.
Date of Action: December 15, 2004
B. Class IIIE Development Actions from December 6, 2004, to December 9, 2004:
1. Memorandum No.: DR05‑069
Project Name: Arlington Homes
Commissioner: The Honorable Ted Schrader
Applicant: Darby Trail Venture, LLC
Location: On the south side of Darby Trails, approximately one-quarter mile east of the intersection of Darby Trails and Curley Road, Section 36, Township 24 South, Range 20 East.
Acreage: 40.40 Acres, m.o.l.
Proposed Development: To divide 40.40 acres into 8 single-family lots and a waiver from Section 306.5, Stormwater Management Plan and Report; Section 306.7, Construction Plan; Section 602.5, Submittal Requirements, Review, and Determination Process; and Section 602.7, Tree Plan.
Type of Action: Denial of the waiver from Section 306.5, Stormwater Management Plan and Report, and Section 306.7, Construction Plan, and approval of the preliminary plan and waiver for Section 602.5, Submittal Requirements, Review, and Determination Process, and Section 602.7, Tree Plan, with conditions.
Date of Action: December 6, 2004
2. Memorandum No.: DR05‑182
Project Name: Hilltop Horizons
Commissioner: The Honorable Ted Schrader
Applicants: H. Allen Altman, Jr., and Laura O. Altman; Daniel C. Johnson and Vicky J. Johnson; and David R. Johnson
Location: On the north side of Frazee Hill Road, approximately 1,950 feet west of the intersection of Powerline Road and Frazee Hill Road, Section 16, Township 24 South, Range 21 East.
Acreage: 34.3 Acres, m.o.l.
Proposed Development: To divide 34.3 acres into 10 single-family lots and a waiver from Section 306.5, Stormwater Management Plan and Report; Section 306.7, Construction Plan; Section 602.5, Submittal Requirements, Review, and Determination Process; and Section 602.7, Tree Plan.
Type of Action: Denial of the waivers for Section 306.5, Stormwater Management Plan and Report; and Section 306.7, Construction Plan; and approval of the preliminary plan and waiver request for Section 602.5, Submittal Requirements, Review, and Determination Process; and Section 602.7, Tree Plan, with conditions.
Date of Action: December 9, 2004
C. Class IIIR Development Actions
None Scheduled