PASCO COUNTY, FLORIDA
INTEROFFICE
MEMORANDUM
TO: Honorable Chairman and DATE: 7/24/02 FILE: GM02-1174
Members of the Board of
County Commissioners
THRU: Bipin Parikh, P.E. SUBJECT: Development Agreement-
Assistant County
Administrator Wesley
Chapel Lakes DRI
(Development Services) BCC
Meeting: 7/30/02, 9:30a.m., NPR
(Cont. from 4/16/02,
4/23/02,
5/7/02, 5/29/02, 6/18/02,
and 7/9/02)
Type
of Action:Public Hearing
FROM: SamuelP. SteffeyII REFERENCES: Comm. Dist.2;
Growth Management
Administrator Planning
Dist.5
It is recommended that the data herein presented be
given formal consideration by the Board of County Commissioners.
DESCRIPTION AND CONDITIONS:
The Florida Local Government Development Act as set
forth in Sections163.3220-163.3243, Florida Statutes, authorizes the use of
development agreements. A development
agreement is designed to encourage a stronger commitment to comprehensive and
capital facilities planning, ensure the provision of adequate public facilities
for development, encourage the efficient use of resources, and reduce the
economic cost of development.
The proposed development agreement between Pasco
County; Wesley Chapel Lakes, Ltd.;
Clearwater Bay Associates, Inc.; Pasco Height Development Corporation; Meadow
Pointe General Partnership; Lee Arnold, Trustee; Meadow Pointe III Community
Development District; and/or other owners within Wesley Chapel Lakes
Development of Regional Impact (DRI), No.166, sets forth the terms and
conditions of development approval with respect to DRI. The purpose of the development agreement is
to set forth the terms and conditions of development approval for Phase I, defined
pursuant to the amended development order as 4,520residential dwelling units
and 220,000square feet of commercial development as the same relates to the
design, right-of-way acquisition, permitting, and construction of the pipeline
project (S.R. 56, east of C.R.581) associated with Phase I of DRI. The property subject to this proposed
development agreement is located in Sections10, 15, 22, 26, 27, 33, 34, and 35;
Township26 South; Range20 East, south of and abutting S.R.54, approximately 3.5miles
east of I-75, extending south to the County line.
ALTERNATIVES AND ANALYSIS:
1.
Continue the
public hearing from July30, 2002, at 9:30a.m., in New Port Richey, to September17,
2002, at 9:30a.m., in Dade City.
2.
Decline to
continue the public hearing.
3.
Decline to hear
the matter.
4.
Direct staff as
to other action desired by the Board.
RECOMMENDATION AND FUNDING:
The
Growth Management Department staff recommends that the Board approve
Alternative No. 1.
No
funding is required at this time.
SPS/ML/gm/weslak27
APPROVED AGENDA ITEM FOR
DATE
BY